A sanctions clause is a provision in an international contract that establishes in advance who bears the consequences of sanctions, export bans, and other regulatory shocks. When the contract is silent on this matter, Italian law does not offer an immediate or unambiguous answer, and a generic force majeure clause is unlikely to provide a safe haven. This article outlines what the clause must include, section by section, with a sample wording for each: relevant sanctions, suspension and termination, authorizations, a no re-export clause, disclosure obligations, advance payments, and orders already accepted.
What I Cover in This Article
- What Italian law provides for when the contract is silent
- When a force majeure clause is not enough
- How to draft a sanctions clause, with sample wording
- Advance payments already made: the no-claims clause and the Reibel case
- How to allocate geopolitical risk in a contract
An Italian company enters into a supply or distribution contract with a foreign counterparty. The relationship proceeds smoothly: orders are confirmed, the goods are produced, and the distributor pays an advance.
Then something changes.
A new sanction prohibits the export of certain products. An administrative authorization is not granted. A bank refuses to process a payment. Or the counterparty proposes to change the destination of the goods and deliver them to a company located in a third country.
At that point, the problem is no longer just one of compliance. It becomes a contractual issue: who must bear the consequences of the regulatory shock?
Can the supplier suspend delivery? Can it terminate the contract? Should it seek authorization? What happens to orders already accepted and advance payments received? And what happens if the performance is not formally prohibited by the law applicable to the contract, but still exposes one of the parties to significant consequences in another jurisdiction?
These are questions that, in international trade, it is increasingly unwise to leave unanswered. Here you’ll find the clause that addresses them, one by one.
My contract doesn’t include anything about this: what does Italian law provide?
Italian law does not provide for a general category of “force majeure” analogous to that found in other legal systems or in certain international instruments.
Events that, in the language of international trade, are classified as force majeure are addressed in our legal system through various provisions and legal categories. In particular, when restrictive economic measures are introduced or expanded, the following may apply:
- 1218 of the Civil Code, which excludes the debtor’s liability when the breach is caused by the impossibility of performance resulting from a cause not attributable to the debtor;
- Article 1256 of the Italian Civil Code, which provides for the extinction of the obligation when performance becomes impossible due to a cause not attributable to the debtor;
- Article 1463 of the Italian Civil Code, which, in contracts involving reciprocal performance, establishes that the party released from its obligation due to supervening impossibility not attributable to it may not demand the consideration and must return any consideration already received. This rule may encounter specific limitations precisely in the context of sanctions, as we will see below;
- Article 1467 of the Italian Civil Code, which allows for the termination of contracts involving continuous, periodic, or deferred performance if the performance of one of the parties has become excessively onerous due to the occurrence of extraordinary and unforeseeable events.
Generally speaking, Italian case law holds that the mere introduction of a restrictive measure does not automatically result in exemption from liability. It is necessary to determine whether, and to what extent, the measure actually renders performance impossible or fulfills the other conditions set forth in the applicable law.
The first conclusion is therefore straightforward: when the contract is silent, the applicable law does not always provide an immediate and unambiguous answer regarding the economic and operational consequences of a regulatory shock. In practice, before suspending a delivery, it is advisable to document in writing which measure applies and why it renders performance impossible or prohibited, because that is precisely what will need to be demonstrated.
My contract includes a force majeure clause: am I protected?
If the contract contains a force majeure clause, the starting point is the clause itself, which must be interpreted to determine:
- which events qualify as force majeure and whether “sanctions” or “governmental actions” are expressly included among them;
- whether the list is exhaustive or merely illustrative;
- what requirements the event must meet, such as unpredictability, inevitability, and being beyond the party’s control;
- whether there are notification requirements and deadlines for invoking the clause;
- what effects result from it: suspension of the obligation, exemption from liability, extension of deadlines, or the right to withdraw or terminate the contract after a specified period.
From this, we draw a second practical conclusion: a clause formulated in entirely general terms that does not precisely define the consequences of the event is unlikely to provide a reliable escape route from a legal relationship that has become prohibited or excessively burdensome.
It is also for this reason that, in international contract practice, the issue is increasingly addressed through clauses specifically dedicated to sanctions: the so-called sanctions clauses.
How should a sanctions clause be drafted in international contracts?
An effective sanctions clause answers five questions: which sanctions apply, what happens when they are triggered, who handles the authorizations, how is the risk of re-export managed, and how can one avoid being caught unprepared. Each section below includes an explanation and an example. The examples are in English because many international contracts are written in English; they are working drafts to be adapted to the specific case, with figures in square brackets to be negotiated, and are not ready-to-use clauses.
The Definition of “Sanctions”
A clause that makes a general reference to “applicable sanctions” immediately raises a question: applicable to whom? Consider a contract governed by the law of State A, entered into between two companies established in States A and B, respectively. A measure adopted by State C might not formally render the performance unlawful under the applicable law and yet produce very significant commercial consequences: because it exposes one of the parties to the risk of secondary sanctions, because a bank or payment network refuses to process the transaction, or because access to a market or an essential link in the supply chain is compromised.
This is not a theoretical problem. In the case of Lamesa Investments Ltd v. Cynergy Bank Ltd, a British bank was required to pay interest to a Cypriot company whose beneficial owner had subsequently been added by OFAC to the list of sanctioned entities. The payment was not prohibited under English law, but it exposed the bank to the risk of U.S. secondary sanctions, including due to its ties to the U.S. financial system. The bank suspended the payments by invoking a contractual clause, and the English Court of Appeal held that this clause could also cover such a risk.
This does not mean that it is prudent to indiscriminately include sanctions from any country at any time in a contract. Overly broad wording can create interpretive uncertainty or conflict with mandatory rules applicable to the parties. The scope must be assessed taking into account, among other things:
- the parties’ place of business;
- the possible existence of blocking legislation or, more generally, mandatory rules to the contrary;
- the markets in which the parties operate;
- the currency and payment systems used;
- the origin and destination of the goods;
- the nature of the services;
- the structure of the supply chain.
Defining which sanctions apply is not merely a matter of drafting. It is a risk allocation decision that must reflect the specific transaction and the parties’ exposures.
“Sanctions” means any economic, financial, or trade sanction, embargo, export control, or other restrictive measure adopted, administered, or enforced by (a) the United Nations; (b) the European Union or any of its Member States; (c) [the United States of America] [the United Kingdom]; or (d) any other authority having jurisdiction over a Party, over the Goods, or over the payment channels used for the transactions contemplated by this Agreement.
“Sanctioned Person” means any person who is the target of Sanctions, including any person listed on a Sanctions list and any person owned or controlled by one or more of them.
Suspension, Termination, and Disclaimer of Liability
Here, too, there is no standard solution. Much depends on the nature of the measure: the counterparty could be a person or entity designated on a blacklist; a ban on exporting certain goods or providing specific services could be imposed; or the transaction could become subject to an authorization regime. Even within the European Union, the multitude of regulations introducing restrictive measures often makes it complex to determine their applicability to a specific relationship. Things become even more complicated when non-European regimes also come into play.
An initial contractual response is the right to temporarily suspend performance or payment if there is reasonable doubt regarding the transaction’s compatibility with applicable measures, for the time necessary to conduct the necessary checks. If the verification confirms a prohibition, it is advisable to expressly provide for the right to terminate the agreement when performance is prohibited or becomes prohibited, to exclude liability for any suspension or termination necessitated by compliance with sanctions (to the extent permitted by applicable law), and to include an indemnification clause for damages arising from violations attributable to the other party.
If a Party has reasonable grounds to believe that the performance of any obligation under this Agreement—including delivery, acceptance of the Goods, or payment—is or may become prohibited by Sanctions, or exposes that Party to a material risk of penalties under Sanctions, that Party may suspend such performance by written notice for the time reasonably necessary to carry out the relevant checks, and in any case for no longer than [30 (thirty)] days.
If performance remains prohibited, or cannot lawfully be performed, for more than [90 (ninety)] days, either Party may terminate this Agreement or the affected orders with immediate effect by written notice.
To the extent permitted by mandatory applicable law, neither Party shall be liable for any suspension or termination of performance that is necessary to comply with Sanctions. Each Party shall indemnify the other against any loss arising from a breach of Sanctions attributable to the first Party.
Authorizations and Licenses
When the transaction requires an authorization—whether from the outset or as a result of a subsequent change in the regulatory framework—it is advisable to specify that the performance subject to a license or derogation is not due until the authorization is obtained and may be performed only in compliance with its conditions. The contract may also specify who is responsible for applying for the authorization, within what timeframe, and what happens if it is definitively denied or not granted within a specified period.
Where the performance of an obligation requires a license, authorization, or exemption under Sanctions, that obligation is not due until such license, authorization, or exemption has been granted, and shall be performed only in compliance with its conditions.
[The Seller] shall apply for the license, authorization, or derogation within [15 (fifteen)] days from [the acceptance of the order] and shall keep [the Buyer] informed. [The Buyer] shall promptly provide all documents and information required for the application.
If the license, authorization, or exemption is definitively denied, or is not granted within [120 (one hundred and twenty)] days, either Party may terminate the affected order by written notice.
The No-Re-Export Clause
Where applicable, the so-called no re-export clause is of particular importance. For certain categories of goods, this approach is no longer merely a matter of good contractual practice. Article 12g of Regulation (EU) No. 833/2014 requires, where applicable, that the exporter contractually prohibit the re-export to Russia or for use in Russia of certain categories of goods and technologies, and that the contract provide for appropriate remedies in the event of a breach. This obligation applies to contracts with operators from non-EU countries, excluding the partner countries listed in Annex VIII of the Regulation. The Commission published a model clause in its FAQs dated February 22, 2024, which should be used as a starting point for goods covered by Article 12g.
The following example is my own working draft—not the Commission’s model clause—and may be used for goods not covered by Article 12g.
The Buyer shall not sell, export, or re-export, directly or indirectly, the Goods to [the Russian Federation] or for use in [the Russian Federation], and shall ensure that its own customers and resellers are bound by an equivalent undertaking.
The Buyer shall notify the Seller without delay of any circumstance that may frustrate the purpose of this clause. Any breach of this clause constitutes a material breach of this Agreement, entitling the Seller to terminate this Agreement and the affected orders with immediate effect by written notice [and to claim a penalty equal to [●]].
Not only addressing the “aftermath,” but also “prevention”
Good contractual practice should not be limited to establishing what to do once a problem has already occurred. It is equally important to provide mechanisms that enable the prevention of violations of the sanctions regime and support the due diligence obligations incumbent upon companies. It may therefore be appropriate to include in the contract:
- a declaration by the other party stating that it is not designated, nor are the entities that own or control it, and that it is not acting on behalf of designated entities;
- an obligation to immediately notify the other party of any new designation or material change in ownership, control, beneficial owner, end user, project location, or payment terms;
- a prohibition on providing, directly or indirectly, services, deliverables, technologies, or other contractual benefits to prohibited entities, territories, or uses;
- the obligation, when necessary, to impose similar restrictions on subcontractors, subconsultants, agents, and sublicensees;
- the right to obtain information and documentation regarding the ownership and control structure, the end-user, and the intended use of the service, as well as to conduct additional checks during the course of the relationship;
- the prohibition on making payments to or from third parties or through accounts other than those previously identified without prior verification.
These checks have taken on particular significance with Legislative Decree No. 211 of December 30, 2025, effective as of January 24, 2026, which implements Directive (EU) 2024/1226 and introduced into the Criminal Code a comprehensive framework governing offenses related to violations of European Union restrictive measures. Article 275-bis of the Criminal Code punishes with imprisonment for two to six years and a fine of €25,000 to €250,000 anyone who, with intent and in violation of restrictive measures, engages in conduct such as making funds or economic resources available to designated entities or entering into prohibited transactions. For certain transactions involving military and dual-use goods, liability also applies in cases of gross negligence. The consequences may affect not only individuals but also the company, through the liability framework set forth in Legislative Decree 231/2001.
The contractual clause does not replace due diligence. However, it can constitute an essential element of due diligence, as it allows for the collection of information, imposes obligations to provide updates, and enables the suspension of performance when circumstances arise that require a more in-depth assessment of the risk of sanctions.
Each Party represents and warrants that neither it nor, to its knowledge, any person that owns or controls it is a Sanctioned Person, and that it is not acting on behalf of a Sanctioned Person.
Each Party shall notify the other without delay of any listing as a Sanctioned Person and of any material change in its ownership, control, or beneficial owner and, with respect to the Buyer, in the end-user, the destination of the Goods, or the payment arrangements.
Upon request, the Buyer shall provide information and documents regarding its ownership and control structure, the end-user, and the final destination of the Goods, and shall allow the Seller to conduct further checks during the term of this Agreement.
Payments shall be made only from and to the accounts identified in [Annex ●]. No payment shall be made by or to third parties, or through different accounts, without prior verification by the receiving Party.
Advance Payments Already Made: The No-Claims Clause and the Reibel Case
The issue of the economic consequences of the termination of the relationship is particularly sensitive. If the recipient of the payment is a designated entity, the return of sums already received—such as advance payments or deposits—may, first and foremost, run afoul of prohibitions on the direct or indirect provision of funds or economic resources. But the problem does not end there. In fact, some sanctions regimes contain specific no-claims clauses, which may prevent the fulfillment of certain claims arising from contracts whose performance has been affected by restrictive measures, even when the counterparty is not itself a designated entity.
The Reibel case, pending before the Court of Justice of the European Union (C-802/24), provides a concrete example. The dispute stems from a 2015 sales contract between the Belgian company Reibel and the Russian company Stankoimport, which had paid an advance. The export of the goods was blocked by European Union restrictive measures, and the delivery was not made. An arbitral tribunal ordered Reibel to return the advance payment with interest, holding that the return would restore the situation prior to the contract and was not prohibited by Article 11 of Regulation No. 833/2014.
The Court of Justice, to which a preliminary ruling was referred by the Swedish Svea hovrätt on November 20, 2024, must determine, among other issues, whether Article 11 also precludes the return of an advance payment relating to goods that were never delivered and the payment of the corresponding interest. In his Opinion of February 26, 2026, Advocate General Biondi proposed answering in the affirmative, further holding that the prohibition falls within the scope of EU public policy and must therefore also be taken into account by the national court called upon to rule on the annulment of an arbitral award. As of November 1, 2026, the Court of Justice had not yet issued a ruling.
From a contractual standpoint, this is an important point: determining when a party may suspend or terminate its performance is not the same as determining who must bear the economic consequences. In contracts most exposed to regulatory risks, it is advisable to expressly provide—to the extent permitted by applicable mandatory rules—for the treatment of orders already accepted, goods already produced, costs already incurred, and advance payments already made. However, the clause cannot override a statutory prohibition: it can only allocate what the law permits to be allocated.
If this Agreement or any order is suspended or terminated under clause [●], the Parties shall agree in good faith on the treatment of accepted orders, Goods already produced, costs incurred, and advance payments received, in each case to the extent permitted by Sanctions and by mandatory applicable law.
Nothing in this Agreement obligates a Party to make or receive any payment, or to satisfy any claim, that is prohibited by Sanctions.
Sanctions Clauses: Decide in Advance Who Bears the Risk
It is impossible to predict what the next geopolitical crisis will be. However, it is possible to determine in advance how the contract should function when that crisis occurs. A good international contract can answer certain fundamental questions in advance:
- which regulatory regimes must be taken into account;
- what information must be provided and updated by the parties;
- when a performance may be suspended;
- what verifications or attempts to obtain authorizations are required;
- when the relationship may be terminated;
- what happens to pending orders and payments already made;
- which law and which dispute resolution mechanism govern the consequences of the shock.
The goal is not to automatically transfer all the risk to one of the parties. Nor is it to include an increasingly lengthy sanctions clause in the contract in the hope of covering every scenario. The real goal is to decide in advance—and with full awareness—how that risk should be distributed, taking into account the specific transaction, the jurisdictions involved, the financial flows, and the structure of the supply chain.
A good clause does not eliminate geopolitical risk nor does it make the unpredictable predictable. However, it can prevent the uncertainty of geopolitics from being compounded—when the regulatory framework changes—by the often avoidable uncertainty regarding what the parties can, must, or can no longer do.
Frequently Asked Questions About Sanctions Clauses in International Contracts
If my contract does not include any provisions on this matter, can I suspend delivery due to a sanction?
It depends. Generally speaking, Italian case law holds that the mere introduction of a restrictive measure does not automatically exempt a party from liability: it must be determined whether the measure actually makes performance impossible or meets the other conditions set forth in the applicable law. When the contract is silent on the matter, the answer is not always immediate or unambiguous.
Does a force majeure clause protect me from sanctions?
Only if it is precisely worded. You must verify the events covered (whether “sanctions” or “governmental actions” are expressly listed), whether the list is exhaustive, the requirements for the event, the notification obligations, and the intended effects. A generic clause that does not specify the consequences is unlikely to provide a reliable loophole.
Which sanctions should be specified in the sanctions clause?
Not those of any jurisdiction at any time: overly broad wording can create uncertainty or conflict with mandatory rules. The scope must be assessed, among other factors, based on the parties’ place of business, blocking legislation, markets, currency and payment systems, the origin and destination of the goods, the nature of the services, and the supply chain.
What happens to advance payments already made if the contract cannot be performed?
This must be expressly provided for. If the recipient is a designated entity, the return of funds may be subject to prohibitions on making funds available, and some sanctions regimes contain no-claims clauses. On this point, the Court of Justice of the European Union has not yet ruled in the Reibel case (C-802/24), in which the Advocate General proposed that the return of the advance payment should also be considered prohibited.
Is the no-re-export clause mandatory?
For certain categories of goods, yes—in contracts with operators from non-EU countries other than the partner countries listed in Annex VIII: Article 12g of Regulation (EU) No. 833/2014 requires the exporter to contractually prohibit the re-export to Russia or use in Russia of certain categories of goods and technologies, with appropriate remedies in the event of a violation. The Commission published a model clause in the FAQs dated February 22, 2024.
Does the sanctions clause replace due diligence?
No. However, it can be an essential element of due diligence, as it allows for the collection of information, imposes obligations to provide updates, and enables the suspension of performance when circumstances arise that require a more in-depth assessment of sanctions risk.